Setting up Projects and Designs > Designs
Management of Design Changes When Synchronizing Designs
When synchronizing design changes between designs in different applications, you can configure preferences for the data synchronization.
For example, if a wire has changed size in a Capital Logic Designer design, you may want to synchronize this data in a Capital Harness Designer design. However, you may not want to synchronize the wire color if Capital Harness Designer is used as the master application for specifying wire colors.
You can these preferences by using the Design Change Policy Manager functionality in Capital Project Manager. See the Capital Project Manager help system for more information.
Parent Topic: