CapitalKnowledge

Capital Harness Designer Modular > Variant Production Module Generation

Simulating Production Technical Variations

There are various ways you can run a simulation process that will automatically show you how many variants of selected PM module(s) will be created, by a full generation, based on their content.

Note

A project preference, Max Number of combinations before failure, controls the maximum number of technical variations to be created per combination. If this maximum is exceeded, the simulation process displays a message in the Technical Variation tab. The message details the preference setting and how many variants would have been created. See “Project Preferences” in the Capital Design Tools - Common Functions User Guide to configure this preference.

Figure 440: Maximum Simulations Exceeded

  • Simulating Production Technical Variations from the PM Module Explorer

  • Simulating Production Technical Variations from the PM Codes Tab

Parent Topic:

Variant Production Module Generation

Capital Harness Designer User Guide, 2512

Unpublished work. © 2025 Siemens