Composite Data Management > Basic Plan
Exporting and Importing
a Basic Plan
You can import and export basic plans from a project in Capital Systems Integrator. The plans are in xml file format.
Prerequisites
The target project (for an import) or source project (for an export) must be open.
The options used in the plan must be available in the target project already.
Procedure
Choose one of the following procedures.
| If you want to... | Do the following: |
|---|---|
| Import a basic plan | Right-click the Plans node in the Project Browser Window on the upper left of the application window and choose Import, or press Space Bar, enter Import Plan, and click the Import Plan ribbon action. An Import Plan dialog box displays. Navigate to the basic plan xml file, select it, and click Import; the plan displays below the Plans node in the Project Browser Window. Note If a design with no associated plan was open and active in the diagram window, the system associates the plan with it. |
| Export a basic plan | Right-click the plan under the Plans node in the Project Browser Window on the upper left of the application window and choose Export. Alternatively, click the plan, press Space Bar, enter Export Plan, and click the Export Plan ribbon action. An Export Plan dialog box displays. Specify the file name and directory where you want to save it, and click Export; the system saves the xml file in the specified location. |
Parent Topic:
Basic Plan
Related Topics
Creating a Basic Plan
Associating a Basic Plan with a Design
Defining Models in a Basic Plan
Capital Systems Integrator User Guide, 2512.2606
Unpublished work. © 2026 Siemens
Source: https://docs.sw.siemens.com/en-US/doc/861057055/202511026.capital_si_user/id9a14a77b-9928-461d-ab79-280e41d38d6e · retrieved 2026-07-18