CapitalKnowledge

Conductors > Nets > Converting Nets to Wires (Interactive Flow) > Shield Termination and Daisy Chain Conversion

Daisy Chain Conversion

On running the Nets to Wires action, daisy chains are removed and a new shield is added in their place, between the new indicator and original pin.

In the example below, the daisy chain from MC400 to MC399 is replaced in by a shield termination, as shown in Figure 105 and Figure 106.

Figure 105: Daisy Chain

  • Pre

Figure 106: Daisy Chain

  • Post

Tip

Multiple multicore indicators can be selected and daisy chained together in one action. See Generating Daisy Chains.

Parent Topic:

Shield Termination and Daisy Chain Conversion

Capital Logic Designer User Guide, 2512

Unpublished work. © 2025 Siemens

Source: https://docs.sw.siemens.com/en-US/doc/861057055/202410078.capital_ld_user/id895e855c-f928-426a-83d5-83f8bea44579 · retrieved 2026-07-18